Aker Solutions Lines Up 50,000-Tonne Statfjord A Recycling Job

Aker Solutions has a letter of intent from Allseas to recycle Equinor's 50,000-tonne Statfjord A topside at Stord, with arrival set for 2029-2031.

Field notes

  1. Letter of intent covers reception, dismantling and recycling of the ~50,000-tonne Statfjord A topside.
  2. Topside arrives at Stord between 2029 and 2031 after removal by Allseas' Pioneering Spirit.
  3. Dismantling and recycling will take about two years and around 100 personnel at peak.
  4. Potential contract valued at $52-156 million (NOK 500 million-1.5 billion); order intake expected Q4 2026.
  5. The topside was originally built at Stord in 1975 and installed on its gravity base in 1976.
Aker Solutions Lines Up Recycling Job for Equinor’s North Sea Platform
PlateAker Solutions Lines Up Recycling Job for Equinor’s North Sea Platform — pasja1000 / pixabay

A 50,000-tonne topside is heading home. Aker Solutions has received a letter of intent from Allseas covering the reception, dismantling and recycling of the Statfjord A topside, Equinor's pioneering concrete-platform development in the North Sea.

The numbers frame the job. The structure should arrive at Aker Solutions' decommissioning facility at Stord, Norway, between 2029 and 2031, according to the company. Dismantling and recycling will run roughly two years and employ around 100 personnel at peak.

If the final contract lands, Aker Solutions expects to book it as order intake in the fourth quarter of 2026 under its Renewables and Field Development segment. The company classifies the potential award as sizeable — a band between $52 million and $156 million, or NOK 500 million to NOK 1.5 billion.

How does the topside actually get to Stord?

The scope splits cleanly between two contractors. Allseas handles the offshore removal with its heavy-lift vessel Pioneering Spirit, the single-lift workhorse of North Sea decommissioning. Aker Solutions then takes over at the quay: preparatory work ahead of arrival, reception, dismantling and recycling of the steel at Stord.

That sequencing matters for the yard. A structure of this scale doesn't arrive on a barge schedule — it arrives on a vessel schedule, and Pioneering Spirit's lifting campaigns are planned years out. The 2029–2031 arrival window gives Aker Solutions time to prepare the site before the topside is ever lifted off its legs.

Why the job closes a 50-year loop

Statfjord A's topside carries its own history at Stord. Workers built it there in 1975 and prepared it for installation on the platform's concrete gravity base structure in 1976 — the start of production from what became one of the North Sea's defining fields.

The yard's relationship with the platform never ended. Aker Solutions has carried out maintenance, modification and life-extension work on Statfjord A across several decades, keeping a structure designed for the 1970s producing well into the 2020s.

So the recycling contract returns the topside to the yard that built it. The steel that left Stord nearly half a century ago comes back to be taken apart, sorted and recycled — a full cycle for one of Norway's oldest offshore installations.

What sits between here and a signed contract?

The letter of intent is not the award. Aker Solutions flags two conditions plainly: the deal remains subject to final contract award, and the order intake would only register in Q4 2026 — meaning a signed contract is more than a year away.

For now, the commercial frame is the "sizeable" classification, Aker Solutions' own tier for jobs between NOK 500 million and NOK 1.5 billion. That puts Statfjord A's topside recycling squarely in the mid-range of the company's decommissioning scope — meaningful, but not transformational against its broader backlog.

The wider context adds weight. Statfjord A is among the earliest concrete platforms in the Norwegian sector reaching end of life, and its removal campaign is a marker for the wave of 1970s-and-1980s-vintage North Sea facilities now moving from production planning to decommissioning execution. Norway's yard capacity for receiving structures of this size is limited, and Stord is one of the few sites with the track record to take them.

The watch item: final contract award, expected to convert into booked order intake in Q4 2026, with first steel from the topside arriving at Stord no earlier than 2029.

via oedigital.com (Source)

Filed under

  • aker-solutions
  • statfjord
  • decommissioning
  • north-sea
  • topsides-recycling
Share this article:

More from Elena Vasquez

Elena Vasquez

Show full bio

News editor covering technology and product news in Oil and gas industry operations and markets at Rig & Refinery.

599 articles

Adjoining reports

« Previous article