Well report · filed November 25, 2026
OffshoreWell report
Masirah Oil reaches Yumna target depth; campaign first oil delayed
Masirah Oil reached target depth at the first well of a new Yumna Field drilling campaign in offshore Block 50, where water depth is 30 metres, but campaign first production is delayed.
Field notes
- The first well in Masirah Oil's current Yumna Field campaign reached target depth in 30-metre water in Block 50 offshore Oman.
- Drilling will proceed from the first well to a second well, but campaign first production has been postponed without a revised startup date.
- Masirah Oil operates Block 50 with a 100% interest and is an indirect 87.5% subsidiary of Jasmine Energy.
- Yumna had yielded 9.07 million stock tank barrels as of Dec. 31, 2024.
- Yumna achieved first oil in February 2020; its Field Development Plan and Declaration of Commerciality were approved in July 2020.

Masirah Oil reached target depth at the first well in its current drilling campaign at the Yumna Field, located in 30-metre water in offshore Block 50, but first production from the campaign has been postponed. The company said drilling would move to the second well and offered no revised startup date.
Masirah Oil operates Block 50, owns a 100% interest in the offshore concession and manages it as one of its key assets. The company is an indirect 87.5% subsidiary of Jasmine Energy. Block 50 spans roughly 17,000 km² in the Gulf of Masirah, east of Oman.
What does the drilling milestone establish?
Masirah Oil stated that “drilling operations would progress to the second well.” The announcement did not disclose a flow test, production rate, reserves addition or revised date. For field operators and service contractors, target depth marks the stated drilling milestone at well one, not the arrival of new production.
The company said it expected further updates as the project developed, and drilling would continue at the second well. Neither the size of the campaign nor its completion date appeared in the update.
In practical terms, target depth confirms progress at the first well, but it does not set a date for new production.
What does the production delay mean?
The postponement concerns first production from the new campaign, not the field’s established output. Masirah Oil gave no replacement date, reason for the delay or estimate of any volume change. It also did not report a production rate from the first well.
Yumna is not an appraisal-stage prospect. The field achieved first oil in February 2020, and Masirah Oil received approval for its Field Development Plan and Declaration of Commerciality in July 2020. The current drilling therefore concerns an already producing field with an approved development and commercial framework. Masirah Oil announced no new sanction, reserve booking, capacity figure or revised schedule for the campaign.
Without a startup date or production estimate, field operators and service contractors cannot yet determine when the campaign will add barrels or how it will affect storage and offloading requirements. Drilling can continue at the second well while that commercial timing remains unsettled.
The delay changes the visibility of new supply, not the field’s established development status.
How did Yumna build its production base?
Yumna had yielded a total of 9.07 million stock tank barrels as of Dec. 31, 2024. That figure measures cumulative field yield through that date; it is not a current production rate or a recoverable-reserve estimate.
The initial discovery, called GA South and later renamed Yumna, came in 2014. It marked the first offshore oil find east of Oman in three decades, following extensive exploration in the area.
Masirah Oil achieved first oil in February 2020. Approval of the Field Development Plan and Declaration of Commerciality followed in July 2020, and production from Yumna-2 and Yumna-3 began in early 2021.
Yumna is a producing asset with a documented operating history, not a prospect awaiting its first commercial approval.
What has changed the field since first oil?
In 2022, Masirah Oil replaced the floating storage tanker and upgraded the mobile offshore production unit (MOPU). Its drilling campaign that year included a workover of Yumna-3 and the drilling of Yumna-4; both were completed by early 2023.
The company’s 2024 multiwell program finished ahead of schedule and below budget. It drilled Yumna-5, which commenced production in April 2024, and performed workovers on three existing wells. Masirah Oil noted that it was “regularly optimising production rates” to “maximise recovery from the field.”
In 2025, the company focused on production facilities and well operations by installing a second flowline between the MOPU and the floating storage and offloading unit. Masirah Oil said the added flowline aimed to improve production-system reliability.
Also during 2025, Masirah Oil began a farm-out process with consultancy Gneiss Energy. The release did not identify a farm-in partner, terms or completion date, so the process did not alter the company’s 100% interest in Block 50. It should not be treated as a completed sale.
The operating base has improved through maintenance and new wells, while ownership remains unresolved because the farm-out is still only a process.
What remains unresolved?
Three items will determine what the drilling milestone means for supply. The first is the result of the second well and whether Masirah Oil maintains its stated sequence. The second is a revised first-production date; the current announcement offers no startup timing. The third is whether the farm-out produces a partner and a defined work program.
Operators should also watch whether the second flowline improves reliability between the MOPU and the storage system, because offshore production depends on keeping oil moving to storage and offloading. Masirah Oil reported the installation under its 2025 program but did not quantify the improvement.
The immediate watch item is a revised first-production date for the campaign, because that date will determine when the new wells can contribute oil.
via Offshore Technology (Source)
More from James Calloway
Show full bio
Staff writer covering people, launches and day-to-day practice in Oil and gas industry operations and markets at Rig & Refinery.
659 articles
Adjoining reports
- Six-Well Campaign Opens for Eni's Coral North FLNG Off Mozambique
- Vaalco advances CI-705 phase with 2028 exploration well commitment
- Chinese Contractor Secures $100m Oil Drilling Contract in Oman
- Saudi Arabia Plans Oil Pipeline Expansion, Asharq Al-Awsat Reports
- Saudi Arabia Weighs Crude Pipeline to Oman, TotalEnergies Chief Says