Venezuela to Ship 65 MMcfd of Perla Gas to Colombia via Idle Pipeline

PDVSA chief Hector Obregon says 65 MMcfd of incremental Perla gas will go to Colombia via a 225-km pipeline idle since years, as Ecopetrol seeks operators hip of its segment.

Field notes

  1. 65 million cubic feet per day of incremental Perla gas is planned for export to Colombia.
  2. Repsol and Eni target Perla output of 645 MMcfd total by first-quarter 2028.
  3. The 225-km PDVSA-built pipeline, inaugurated in 2007, has been idle and needs repairs.
  4. Ecopetrol wants operators hip of Colombia's 88-km segment and a 10-year sale-purchase deal.
  5. Venezuela's gas deficit has driven years of power outages and rationing.
Venezuela Plans Colombia Gas Exports from Perla Offshore Field
PlateVenezuela Plans Colombia Gas Exports from Perla Offshore Field — avantrend / pixabay

Some 65 million cubic feet per day of incremental gas from Venezuela's Perla offshore field is set to be exported to Colombia through a cross-border pipeline that has sat idle for years and needs repairs before it can flow again.

PDVSA president Hector Obregon laid out the plan on Friday at a conference in Caracas, framing it as part of a recently signed agreement to secure initial gas supplies for Venezuela's neighbor. Colombia, he noted, increasingly needs gas for domestic use.

Who operates Perla — and when does the gas arrive?

Spain's Repsol and Italy's Eni operate the Perla project, in the Gulf of Venezuela. Earlier this year, the two companies said the output increase — taking Perla to a total of 645 million cubic feet per day — would be available by the first quarter of 2028.

That timeline matters. The 65 MMcfd destined for Colombia is incremental production, not gas Venezuela can spare today.

The push sits inside a broader effort: a Washington-backed reconstruction plan under which Venezuela is trying to revive a gas industry whose output currently falls short of what the country needs for electricity generation. That deficit has contributed to years of power outages and rationing.

The expectation, according to Obregon, is that incremental output from onshore and offshore projects combined will be enough to close the domestic gap and open the door to exports.

What is Ecopetrol asking for?

On the Colombian side of the border, Ecopetrol is moving in parallel. CEO Joaquin Gutierrez told a corporate earnings call on Friday that securing supplies through the binational gas pipeline ranks among the company's priorities.

"We will ask PDVSA to be granted operationship on Colombia's 88-kilometer segment and are negotiating a 10-year sale-purchase agreement at a very competitive price," Gutierrez said.

The comments signal Bogota's willingness to take operational responsibility for its stretch of the line — an arrangement that could ease the repair and reopening workload for PDVSA, whose maintenance capacity has been stretched thin.

Venezuela's oil ministry did not immediately reply to a request for comment.

What shape is the pipeline in?

The pipeline itself is a 2015-vintage ambition that never quite paid off. Built by PDVSA and inaugurated in 2007, the 225-kilometer line has remained idle in recent years. Repairs are required before it can be brought back into service, and no reopening date has been announced.

The Colombian segment accounts for 88 kilometers of the total. If Ecopetrol takes operators hip of that portion, roughly 137 kilometers of the line would remain PDVSA's responsibility on the Venezuelan side.

For context on scale: the 65 MMcfd slated for export is about a tenth of Perla's projected 645 MMcfd capacity once the expansion lands in early 2028. Most of the field's output would stay in Venezuela.

What to watch

Three items will determine whether this deal produces molecules.

  • The repair schedule. Neither PDVSA nor Ecopetrol has published a cost estimate or timeline for rehabilitating the 225-km line.
  • The contract terms. Gutierrez's "very competitive price" comment is his characterization, not a published number; the 10-year sale-purchase agreement is still in negotiation.
  • Perla's ramp-up. Repsol and Eni have targeted first-quarter 2028 for the output increase to 645 MMcfd. Any slip pushes the export start with it.

The watch item is the pipeline repair timeline — without it, the agreement stays a signature on paper.

via oedigital.com (Source)

Filed under

  • venezuela
  • colombia
  • perla-field
  • natural-gas-exports
  • cross-border-pipelines
Share this article:

More from Elena Vasquez

Elena Vasquez

Show full bio

News editor covering technology and product news in Oil and gas industry operations and markets at Rig & Refinery.

599 articles

Adjoining reports

« Previous articleNext article »