Eni Locks In Contracts for Cronos Gas Build-Out Offshore Cyprus
Eni has signed EPC and drilling contracts for the Cronos gas project offshore Cyprus, a 3-tcf development targeting 500 MMscfd and first gas in H1 2028 via Egyptian LNG.
Field notes
- Eni signed EPC and drilling contracts for the Cronos project in Block 6, offshore Cyprus, following a July 2026 FID.
- Cronos holds an estimated 3 trillion cubic feet of gas initially in place, per Eni.
- Peak production is designed at up to 500 million standard cubic feet per day, with first gas expected in H1 2028.
- Gas will be processed at Egypt's Zohr facility and liquefied at the Damietta LNG plant for export to Europe.
- Eni Cyprus operates Block 6 at 50%, with TotalEnergies as partner.

Eni has signed the core engineering, procurement, construction and drilling contracts for the Cronos gas project in Block 6, offshore Cyprus, kicking off the execution phase of a development designed to deliver up to 500 million standard cubic feet of gas per day.
The signing follows a final investment decision taken in July 2026 to develop the Cronos field, and it moves Cyprus a concrete step closer to commercialising its offshore gas resources in the eastern Mediterranean. Eni's subsidiary Eni Cyprus operates Block 6 with a 50% stake; TotalEnergies holds the partner position.
A formal ceremony in Nicosia marked the launch, drawing Cyprus President Nikos Christodoulides, Minister of Energy, Commerce and Industry Michael Damianos, and Eni's global natural resources chief operating officer, Guido Brusco.
The takeaway: the paperwork is done and the rigs, vessels and fabrication yards are next.
What do the contracts cover?
The package Eni has finalised spans essentially the full hardware list for a deepwater gas development:
- A floating control unit
- Subsea production systems
- Offshore transportation and installation
- Sealines
- Flexible pipes and umbilicals
- Onshore engineering, procurement and construction
- Drilling rig services
Together, these awards give the project everything it needs to move from planning into steel and wells. Eni has not disclosed contract values or the individual contractors in its announcement.
How big is Cronos, and how fast can it flow?
According to Eni, the Cronos field holds an estimated three trillion cubic feet of gas initially in place — a resource figure rather than a certified reserve number, and worth keeping in that frame when comparing it with neighbours.
Peak production is designed for up to 500 million standard cubic feet per day, with first gas expected in the first half of 2028. That timeline is ambitious for a deepwater project, and Eni is leaning on what it calls a fast-track approach to hit it: rather than building standalone export infrastructure, the development will tap regional facilities that already exist.
In short, the schedule depends on integration, not invention.
Where does the gas go?
Cronos production will head to Egypt. There it will be processed at established sites — Eni cites the Zohr facility, the giant field it brought online in the Nile Delta — before being liquefied at the Damietta LNG plant and shipped onward to Europe.
The routing matters. It gives Cypriot gas a route to market without a new Cyprus-based LNG terminal, and it feeds European buyers hungry for non-Russian molecules. It also deepens the Eni-built link between Cypois's acreage and Egypt's processing and liquefaction backbone.
For Egypt, additional feed gas for Damietta supports its own export ambitions at a time when domestic demand has periodically squeezed LNG shipments.
Eni's wider Cypriot position
Eni has operated in Cyprus since 2013. Beyond Block 6, the company runs Block 8 and holds stakes in Blocks 7 and 11, with TotalEnergies acting as operator on the latter two.
That footprint gives Eni, with TotalEnergies alongside, the largest consolidated position among international players in Cyprus's exclusive economic zone — and Cronos is positioned as the first concrete move to monetise it.
What to watch next
The watch items are the drillship mobilisation, the first steel cut on the floating control unit, and confirmation that the first-half 2028 first-gas target survives contact with execution. Block 6's success or slip will also shape the pace at which Eni and TotalEnergies move on their other Cypriot holdings.
For now, the contracts are signed in Nicosia, and the clock on 2028 is running.
via Offshore Technology (Source)
More from Elena Vasquez
Show full bio
News editor covering technology and product news in Oil and gas industry operations and markets at Rig & Refinery.
555 articles
Adjoining reports
- Eni Takes 100% of Sapukala Deepwater Block in Kutei Basin
- Saipem lands $2-billion FPSO contract for Eni-Petronas gas project
- Saipem secures $2 billion FPSO contract from Eni–Petronas venture
- Yinson Productions secures topside modification scope on Eni FPSO
- Eni and Libya's NOC open tender for pipeline and subsea works