Giga Energy Signs $1 Billion, 10-Year Lease for 60-MW Texas AI Campus
Houston's Giga Energy signed a 10-year, ~$1 billion lease with an unnamed U.S. AI cloud provider for a 60-MW data center in Hunt County, Texas, targeting spring 2027 startup on an eight-month modular build.
Field notes
- Giga Energy signed a 10-year lease valued at approximately $1 billion with an undisclosed U.S. AI cloud provider.
- The 60-MW Project Marl campus spans ~30 acres in Hunt County, Texas; construction began July 2025 with startup targeted for spring 2027.
- Modular construction is expected to complete the facility in under eight months.
- Construction supports ~300 jobs; operations will create 24 permanent positions.
- The closed-loop cooling system requires no municipal or groundwater for cooling computing equipment.

A 10-year lease valued at roughly $1 billion anchors Giga Energy's 60-megawatt data center campus in Hunt County, Texas. The Houston-based developer signed the agreement with an undisclosed U.S. artificial intelligence cloud provider. The deal signals where AI computing money is flowing next: into power infrastructure itself.
Giga Energy announced the lease Tuesday. Construction began in July on the approximately 30-acre campus, which the company calls Project Marl. Operations are expected to start in spring 2027.
What does the deal actually cover?
The numbers deserve scrutiny. Giga Energy has not disclosed the cloud provider's identity, the detailed lease economics, or the project's total construction cost. The roughly $1 billion figure is the announced value of the 10-year lease — not necessarily the capital expenditure required to build the facility. That distinction matters for anyone sizing the investment.
Giga Energy will own and operate the facility under the long-term lease. For natural gas producers and power generators, the takeaway is straightforward: AI infrastructure is a potential source of sustained electricity demand. Facilities needing reliable, around-the-clock power could support investment in dispatchable generation (power plants that can be ramped up on demand, including gas-fired units), alongside renewables, storage and transmission.
In short: this is a contracted revenue story, not yet a construction-cost story.
How fast can it be built?
Giga Energy is betting on modular construction, relying on factory-manufactured components assembled on-site. The company expects to finish the facility in less than eight months, a sharp contrast with the longer schedules typical of conventional data centers. That claim is the company's own and has not been independently benchmarked here.
Construction is expected to support approximately 300 jobs. Completed operations will create 24 permanent positions. The company also expects recurring local tax revenue, though actual economic benefits depend on operations and applicable tax arrangements. Twenty-four permanent jobs on a $1 billion lease value is a ratio local officials will weigh carefully.
Water and power: the two constraints
The development uses a closed-loop cooling system designed to operate without municipal or groundwater supplies for cooling computing equipment. Giga Energy said water consumption will be limited primarily to ordinary employee and building needs. That addresses one of the loudest criticisms of large computing facilities — their draw on local water resources.
Electricity infrastructure is the other central piece. The campus will connect to underutilized capacity through dedicated electrical infrastructure, according to the developer, rather than relying on distribution capacity serving existing residential and commercial customers. No interconnection agreement, utility partner or grid operator was named in the announcement.
Why does this matter for the energy trade?
Texas keeps attracting data center development on the strength of its industrial infrastructure, available land and expanding electricity market. But rapid growth in computing demand is drawing sharper scrutiny of grid reliability, generation capacity and how infrastructure costs get allocated among customers.
For utilities and electrical equipment suppliers, additional data center construction could lift demand for transformers, substations, grid connections and related hardware. The ability to deliver electricity on schedule may increasingly decide where AI facilities get built — a siting criterion that sits outside any chip roadmap.
Institutional investors and family offices eyeing the sector face a harder task: separating long-term contracted revenue from development costs and from the risks of securing sufficient power capacity. The Giga Energy agreement illustrates the point. AI investment now extends beyond computing technology into energy infrastructure, where electricity access, construction efficiency and operating costs drive project economics.
The watch item
Spring 2027 operations, on an eight-month modular build that started in July. Watch whether Giga Energy names its cloud tenant, discloses the interconnection details behind that dedicated power infrastructure, and confirms the construction timeline it has promised. The lease value is announced; the delivery is not yet demonstrated.
via oilandgas360.com (Source)
More from Priya Raman
Show full bio
Senior reporter covering technology and product news in Oil and gas industry operations and markets at Rig & Refinery.
645 articles
Adjoining reports
- Google Buys 50 MW From Quaise's Superhot Geothermal Play in Oregon
- Midstream M&A queue builds behind AI-driven data-center gas demand
- Kentucky Power Proposes 760-MW Big Sandy Gas Plant for TeraWulf
- TC Energy sanctions C$6bn of gas projects as data-centre demand drives growth
- $480 Million DOE Loan to Arena Energy Targets Gulf Redevelopment