Qatar Tables 1,650 MW and 20 Years of LNG for Lebanon's Grid
Qatar's draft program for Lebanon pairs two 825-MW gas plants on a three-year build with a 20-year QatarEnergy LNG contract, financed privately and priced at zero upfront cost to Beirut.
Field notes
- Qatar proposes two 825-MW gas-fired power plants for Lebanon, built within three years.
- QatarEnergy would supply gas under a 20-year LNG contract.
- Private financing replaces Lebanese public money; no upfront cost to Beirut.
- Payment obligations and guarantees remain open for negotiation in the draft.
- Lebanon's state utility currently supplies only a few hours of electricity per day.

Two gas-fired plants totalling 1,650 megawatts and a 20-year LNG supply contract sit at the centre of a Qatari proposal that would hand Beirut generating capacity within three years at no upfront cost to the Lebanese state.
A draft of the National Integrated Energy Investment Program, seen by Reuters, has Qatar building two 825-MW gas-fired power plants and QatarEnergy supplying the feedstock under a 20-year LNG arrangement, with private financing standing in for Lebanese public money.
The scale of the offer matches the depth of the problem. Lebanon's state utility currently delivers only a few hours of electricity a day, a deficit that has persisted through years of fuel shortages, currency collapse and unpaid fuel contracts. The program, if executed as drafted, would more than double what the grid reliably provides and replace a patchwork of private diesel generators that households and businesses run at several times the tariffed cost of state power.
What does the plan actually contain?
The draft program breaks into three committed elements:
- Two 825-MW gas-fired power plants, built inside a three-year window.
- A 20-year LNG supply contract with QatarEnergy feeding those plants.
- Private financing in place of Lebanese public money, removing the upfront capital burden from Beirut.
What the document does not contain matters just as much. It leaves payment obligations and guarantees open for negotiation. That gap is the hinge of the whole proposal: construction and supply can be sketched in detail, but nothing proceeds until Qatar and Beirut agree on who pays, on what schedule, and against what security — questions Lebanon's negotiators have struggled to answer with previous suppliers.
For practitioners, the structure is familiar. This is a contractor-financed energy service model, not a concession or an asset sale: Qatar takes development and fuel-supply risk in exchange for a long-dated offtake, and the Lebanese state's exposure begins only when electrons flow.
How firm is it?
Sanctioned project or appraisal-stage paper? Right now, paper. The program is a draft; no signing date, no contractor selection, no land, and no tariff structure appears in the reported document. The three-year build timetable reads as a planning assumption, not a schedule anchored to an engineering, procurement and construction award.
The precedent cuts both ways. QatarEnergy has supplied Lebanon before through short-term arrangements, and Gulf financing for Levantine infrastructure has a record of stalling on sovereign-guarantee questions. The 20-year tenor signals seriousness about staying in the market; the open payment terms signal that the hard bargaining has not started.
Who carries the risk?
Under the draft, Qatar absorbs construction risk and fuel-supply risk. Lebanon's residual exposure concentrates in offtake: paying for gas and power over two decades in hard currency, through a utility that cannot currently collect enough revenue to cover its own diesel bills.
Private financing softens but does not erase that problem. Lenders to the vehicle — whoever they prove to be — will demand either state guarantees or ring-fenced receivables, and it is exactly that demand the document defers to negotiation.
What changes for the market if it lands?
For LNG traders, a 20-year Qatari contract into the East Mediterranean adds a fixed-destination flow to a region that has mostly bought spot. For regional gas politics, it would position Qatari molecules against Egyptian and potentially Israeli supply into a market of roughly six million people whose unmet demand is chronic.
For Lebanon's industrial base, reliable baseload at 1,650 MW would be the largest single improvement to the operating environment in a generation.
What to watch
The open items are the ones that decide everything: the payment mechanism, the guarantees, and whether Beirut can secure parliamentary cover for a two-decade commitment. The next signal will be the move from draft program to signed agreement — no date yet attached — and whether Qatar names the private financing partners before or after that signature.
Until the payment terms close, the 1,650 MW remains an offer, not a project.
via reuters.com (Original)