Well report · filed November 19, 2026
Gas & LNGWell report
West Virginia PSC Clears $2.48B, 1,200-MW Gas Plant at Maidsville
West Virginia's PSC approved a $2.48 billion, 1,200-MW combined-cycle gas plant at Maidsville plus 70 MW of solar, with a construction surcharge hitting customer bills first.
Field notes
- West Virginia PSC granted a certificate Tuesday for the $2.48B, 1,200-MW Maidsville Energy Center gas plant.
- The combined-cycle plant will sit next to the Fort Martin coal plant in Monongalia County, with startup targeted late 2031.
- The same order approved 70 MW of solar across three sites at $182 million.
- A surcharge will make existing customers pay financing costs during construction.
- The United Mine Workers and the Sierra Club opposed the project and lost.

The Public Service Commission of West Virginia on Tuesday granted FirstEnergy subsidiaries Mon Power and Potomac Edison a certificate of public convenience and necessity — the state siting approval — to build a 1,200-megawatt combined-cycle natural gas power plant in Monongalia County. The project carries a $2.48 billion price tag. Targeted startup is late 2031.
The new unit, named the Maidsville Energy Center, will sit adjacent to the aging Fort Martin coal plant in Maidsville. The combined-cycle configuration (a design that recovers waste heat from the gas turbine to drive a second steam turbine) makes it the largest single generation investment approved in the state in years. The applicant is First Energy Corp.'s Mon Power and Potomac Edison subsidiaries.
In the same order, the PSC approved 70 megawatts of solar capacity across three sites at a cost of $182 million. That brings the total sanctioned package to roughly $2.66 billion in new generation for the two utilities.
The takeaway: West Virginia's regulator has put gas — not coal, not renewables alone — at the center of the state's next decade of power supply.
What did the commissioners approve?
Three distinct items moved together in the ruling.
- The 1,200-MW Maidsville Energy Center, a $2.48 billion combined-cycle gas plant sited next to the Fort Martin coal station in Maidsville, Monongalia County.
- A 70-MW solar portfolio spread across three sites, costed at $182 million.
- A financing surcharge that allows the utilities to collect construction-carrying costs from existing customers before the plant enters service.
That surcharge drew opposition, and it is the element with the most immediate effect on ratepayers. Customers of Mon Power and Potomac Edison will begin paying financing costs during the construction period rather than after the 2031 startup, shifting cost recovery several years earlier than a traditional post-completion rate case would allow.
Who lost this round?
The United Mine Workers and the Sierra Club both opposed the certificate and came away empty-handed. The coal miners argued the gas plant undermines fuel and jobs tied to the existing coal fleet, including the Fort Martin unit next door. The Sierra Club challenged the gas build on environmental grounds. The commission rejected both lines of opposition and granted the certificate in full.
No party announced an appeal in the immediate aftermath of the order, though intervenors in West Virginia certificate cases retain the option to seek rehearing.
What happens next?
Construction timing now drives the story. The utilities target late 2031 for commercial operation of the Maidsville Energy Center, a schedule that typically requires notice-to-proceed with the turbine supplier and site work well before the end of the decade. Watch for the engineering, procurement and construction award, the interconnection schedule at the Fort Martin site, and the first surcharge line items appearing on customer bills.
The watch item: whether the 70-MW solar portfolio and the gas plant hold to the sanctioned $2.66 billion combined budget as procurement begins, and whether labor and environmental intervenors seek rehearing on the certificate.
via marcellusdrilling.com (Source)
More from Olivia Hart
Show full bio
Correspondent covering technology and product news in Oil and gas industry operations and markets at Rig & Refinery.
633 articles
Adjoining reports
- Appalachian Power Commits $17 Billion to 3 GW of Gas Plants in West Virginia
- North Carolina Approves 2,730 MW of New Duke Gas Plants
- Kentucky Power Proposes 760-MW Big Sandy Gas Plant for TeraWulf
- PPL Lifts Capex to $25 Billion for 645-MW Kentucky Gas Plant
- Georgia Power's 20% Battery Rating Tilt Could Hand Gas Its Next 6,000 MW