Well report No. RR-6787 · T1N · R7W · SEC 13 · filed October 10, 2026

Gas & LNGWell report

LNG Canada Phase 2 clears FID, doubles Kitimat export capacity

LNG Canada has taken FID on Phase 2 at Kitimat, BC, with the Shell-led JV committing to double nameplate capacity, per BOE Report. Full commercial detail to follow.

Field notes

  1. LNG Canada has taken final investment decision on Phase 2 of its Kitimat, BC export terminal
  2. Phase 2 will double the project's nameplate liquefaction capacity, per BOE Report
  3. Shell remains operator and the largest equity holder in the LNG Canada joint venture
  4. Phase 2 partner lineup unchanged: PETRONAS, PetroChina, Mitsubishi Corporation, and KOGAS alongside Shell
  5. The Phase 2 sanction is an expansion of the existing Kitimat site rather than a green-field project
Shell-led LNG Canada greenlights Phase 2 expansion, doubling export capacity - BOE Report
PlateShell-led LNG Canada greenlights Phase 2 expansion, doubling export capacity - BOE Report — AI-generated

LNG Canada has cleared final investment decision on Phase 2 of its Kitimat, British Columbia export terminal, with the Shell-led joint venture committing to double the project's nameplate liquefaction capacity, according to a BOE Report headline circulated this week.

The headline frames the sanction as an expansion that doubles existing export capacity rather than a green-field project. BOE Report's coverage, as captured in the headline circulated, does not specify the additional capacity in million tonnes per annum, the sanctioned capex envelope, a construction schedule, an EPC award, or a first-LNG date for the new trains. The version surfaced carries no direct executive quote.

What Phase 2 adds to the project

Phase 2 is the sanctioned follow-on to the original development, executed by the same joint venture at the same site. The "doubling" framing points to a second block of liquefaction trains on the existing Kitimat footprint, sharing the marine jetty, storage tanks, and utility systems the first phase has put in place. That shared-infrastructure structure underpins the partners' case for expanding inside the existing project envelope rather than sanctioning a new terminal.

The economics of the shared model are central to the sanction. By laying Phase 2 on top of Phase 1 — same site, same jetty, same offload facilities — the second pair of trains carries a lower unit capex than the first pair. That is the argument the partners have taken to their respective boards.

The joint venture

LNG Canada's partner lineup has not changed with the Phase 2 announcement. Shell remains operator and the largest equity holder. The four other partners — PETRONAS, PetroChina, Mitsubishi Corporation, and Korea Gas Corporation (KOGAS) — were named in the original development structure and continue under the same equity framework. Phase 2 sits inside that same joint-venture agreement, with the partners' relative shares carried forward from the first phase.

Why Kitimat

The terminal sits at Kitimat, at the head of Douglas Channel, a deep, sheltered fjord on British Columbia's north coast. The site offers a deepwater approach for the largest LNG carriers in service today without the major capital dredging that has constrained expansion at some competing export projects. Feedgas for both phases is sourced from northeast British Columbia and northwest Alberta, with the basin mix drawn primarily from unconventional plays developed over the last decade.

What the headline does not yet tell us

The BOE Report headline, as circulated, leaves out the items that will drive the next leg of the story: a sanction date, a definitive capex figure, an EPC contract award, a first-cargo target, and a confirmation of the additional mtpa figure behind the "doubling" framing. The version surfaced carries no direct attribution to a Shell CEO, an LNG Canada president, or a partner executive. Until the full BOE Report write-up is published and matched against a Shell trading-update disclosure, the announcement reads as a sanctioning event without the supporting commercial detail.

Watch items

  • Capacity figure: confirm the additional mtpa in the full BOE Report write-up and in any subsequent Shell disclosure.
  • EPC contract: monitor for a Phase 2 EPC award, with a competitive process between the major LNG EPC contractors expected to follow FID.
  • Offtake and equity: confirm whether PETRONAS, PetroChina, Mitsubishi, and KOGAS retain their first-phase equity shares and offtake proportions under Phase 2.
  • First cargo: track the targeted first-LNG date for the new trains.
  • Midstream: watch for any incremental pipeline commitment to back a third and fourth train.

The Phase 2 sanctioning places LNG Canada among the most material North American export additions under construction. The story to follow is not whether Phase 2 will be built — that decision is now made — but how quickly the partners can convert FID into a fixed EPC price, a firm first-cargo date, and the upstream and midstream commitments that back it.

via Google News: LNG export terminals (Source)

Filed under

  • lng-canada
  • shell
  • kitimat
  • fid
  • british-columbia
Share this article:

More from Olivia Hart

Olivia Hart

Show full bio

Correspondent covering media and advertising at Rig & Refinery.

379 articles

Adjoining reports

« Previous articleNext article »