Well report · filed November 23, 2026

Gas & LNGWell report

Ohio board clears 800-MW Ashville gas plant after 81% voter rejection

The Ohio Power Siting Board approved an 800-MW gas plant for EdgeConneX's Ashville data center after 81% of village voters rejected the deal; foes have 30 days to seek review.

Field notes

  1. The Ohio Power Siting Board approved an 800-MW natural gas plant for EdgeConneX's Ashville data center complex in a 108-page opinion.
  2. 81% of Ashville voters rejected the April resolution backing the project on Election Day.
  3. EdgeConneX agreed to pay up to $102 million toward municipal, school and community work.
  4. The plant will not connect to the grid at large; it will serve only the on-site computing warehouses.
  5. Opponents have 30 days to seek reconsideration before a possible appeal to the Ohio Supreme Court.
Ohio OKs gas plant for data centers despite local voter backlash
PlateOhio OKs gas plant for data centers despite local voter backlash — Tama66 / pixabay

The Ohio Power Siting Board has approved an 800-megawatt natural gas plant to serve a data center complex in Ashville, a central Ohio village where 81% of voters rejected the same project on Election Day.

The board's 108-page opinion finds developer EdgeConneX met the statutory requirement that the project serves the public interest. The plant will not connect to the state's grid at large; it will supply only the computing warehouses under development on the Ashville site.

Regulators cited the project's economic benefits, backing from the Ashville Village Council and the local school district, and EdgeConneX's promises to limit noise and set construction hours. The approval is not unusual in kind: data center developers across the United States have pressed ahead with controversial plans for gas-fired generation, and critics say the Ohio ruling highlights how the state treats fossil fuels compared with solar and wind.

In April, the council passed a resolution endorsing the project after EdgeConneX agreed to pay up to $102 million toward municipal, school and community work. Some residents gathered signatures for a referendum on that agreement, and 81% of village voters went against it.

What did the board do with the election result?

The board noted the Ashville vote in its decision and asserted authority to issue the permit regardless of how residents voted. It found that conditions agreed to by the village, the developer and board staff were enough to handle public concerns. The site sits close to homes, a playground, a park and a soccer field.

State Rep. Tristan Rader, a Democrat and ranking minority member of the Ohio House Energy Committee who took part in the case as a nonvoting member of the Power Siting Board, said: "There's a huge double standard for fossil fuels and renewables in the state of Ohio." During the board's Nov. 19 meeting, he said the plant "is literally going to be throwing a shadow on these communities."

Takeaway: the board treats a village vote as context, not as a veto on a project it has already found in the public interest.

Why did a gas plant clear a bar that solar and wind did not?

The board has denied multiple solar projects on the basis that local opposition outweighed economic benefits, or has proposed permit conditions aimed at addressing community concerns, said Chris Tavenor, general counsel for the Ohio Environmental Council, which was not a party to the case.

"In this case, the Board does the exact opposite, using those community benefits and conditions to justify ignoring local concerns," Tavenor said in an email.

In 2025, board staff recommended against the Grange Solar project in Logan County because of pushback from local governments, even though a majority of individual commenters wanted the solar farm. The developer withdrew and pursued projects elsewhere.

Earlier this year, the board rejected the Crossroads Solar farm in Morrow County after every nearby local government opposed it. That ruling cited the "presence of strong, united opposition," though the developer's own analysis found that dozens of comments were fake and that verifiable opponents were not overwhelming compared with supporters. Board staff also reversed course after one township shifted from neutral to opposed.

"Ultimately, the Ohio Power Siting Board has demonstrated its hypocrisy," Tavenor said, "by approving a natural gas facility for a data center where it has denied renewable energy projects with less significant opposition."

Takeaway: the same body that blocks renewables over local opposition now counts a village council's endorsement as a reason to approve gas generation.

What does the plant's design say about its emissions?

Opponents argued that the proposal fails a separate legal requirement that projects have minimal environmental impact. EdgeConneX chose reciprocating internal combustion engines and simple-cycle natural gas turbines over less-polluting combined-cycle turbines or fuel cells, which cost more right now.

Regulatory staff argued that "minimum" does not demand the lowest environmental impact but depends on a plant's purpose, available technology and economics. The board agreed the project meets the requirement and left air permitting to the Ohio Environmental Protection Agency, which is expected to issue permits for the facility.

Takeaway: the siting decision routes emissions review to Ohio EPA rather than resolving it at the board table.

What happens next?

Project opponents have 30 days to ask the Power Siting Board to reconsider the ruling. If the board does not change its mind, an appeal to the Ohio Supreme Court could follow.

Watch the 30-day reconsideration window and the Ohio EPA air permits: those two steps decide whether EdgeConneX's 800-MW plant ever runs, and whether Ashville's 81% vote becomes a court record.

via canarymedia.com (Source)

Filed under

Share this article:

More from James Calloway

James Calloway

Show full bio

Staff writer covering people, launches and day-to-day practice in Oil and gas industry operations and markets at Rig & Refinery.

656 articles

Adjoining reports

« Previous articleNext article »